1. Arrive at the venue and take inventory of equipment and materials
2. Clear the site, whitewash the walls, and review the dimensions and obstacles on the site
3. Lay floor MATS, floor glue, erect fences, and divide areas.
4. Build the steel frame, enclose the net and cover the PVC tube
5. Lay the platform board
6. Set up decorative panels
7. Install devices one by one according to the area CAD analysis diagram
8. Power debugging of electronic equipment
9. Final acceptance